市场调查报告显示,随着消费者对于丰胸趋向理智粉嫩公主酒酿蛋,健康安全越来越受到重视。在此背景下,倡导健康丰胸、安全丰胸酒酿蛋丰胸产品、天然丰胸、自然丰胸的粉嫩公主酒酿蛋,以绝对性的优势继续领衔丰胸产品排行榜酒酿蛋丰胸,销量遥遥领先,不仅赢得了女性朋友的一致好评,更成为广大女性朋友丰胸的不二选择产后丰胸。

New Propane Gas Compressor Project for ONGC, Uran

New Propane Gas Compressor Project was awarded by ONGC as a part of revamp of LPG plant at ONGC, Uran with a targeted completion period of 22 months with PMC EIL Baroda. The project had to be built in a gas processing plant which was 30 years old.

Though the project size was relatively small; all engineering disciplines were critical to it. viz. RCC foundation of 10 micron vibration tolerance, structural shed design to withstand a wind speed of 65 KMPH, mechanical piping with majority LTCS pipes and mechanical installation of 3.35 mega watt centrifugal compressor with HT motor. Electricals consisting of HT and LT feeder modification and its revamping along with shifting of 10 MW load. And finally instrumentation including sil-3 PLC and DCS hook-up apart from field instruments and cabling. Moreover, Savair had to address critical Process Design Challenges as a part of the plant data was not available in the old plant.

Technology Partners

IHI Corporation, Japan & Dresser Rand, India

Challenges

The biggest challenge for this contract was getting the compressor delivery on time as Japan was struck by a Tsunami in the month of March 2011. The second challenge was working in a 30 year old plant and the site was very close to the compressor house where extra safety measures were required to be taken since it was the most hazardous zone of the entire plant. The third challenge in the project was to carry out the job in the Brown field without interrupting the production of LPG adhering to all stringent safety requirements. The project was completed successfully with zero accidents.

SALIENT FEATURES
  • Four stage Centrifugal PG Gas Compressor coupled with 3.35 MW HT motor.
  • Reciprocating Compressor for Evacuation.
  • All critical Piping was of LTCS up to 24 Inch
  • Structural shed design with high wind speed of 65 KMPH
  • Critical foundation vibration tolerance 10 microns
  • Static propane refrigerated vessels for storage and heat exchangers etc.
  • Material handling EOT crane 10 mt
  • Electrical – HTLT feeder modification, revamping and shifting of 10 MW loads
  • Hi-end SIL – 3 PLC
  • DCS hook – up with existing plant

SAVAIR ENERGY LIMITED
SAVAIR HOUSE, A-564, TTC Industrial Area,
Mahape, Navi Mumbai - 400 710, INDIA.
Tel - +91 22 2778 1916 / 17
FAX - +91 22 2778 1935
Email - sales@ savair.co.in | projects@savair.co.in